You are here >> DESI Power Economics > Triple - bottom line performance of Baharbari project

.................................................................................................................................................................

Cost of Electricity Generation by
Biomass-based Power Stations

Economics of Baharbari EmPower Partnership projects
Triple - bottom line performance of
Baharbari project
Financial Benefits
.................................................................................................................................................................

Triple - bottom line performance of Baharbari project

Typical "Triple Bottom Line" Performance of an EmPower Partnership Project
(with a 50 kWe biomass gasification power plant)

Machines and Equipment
Economic Performance
Social Performance
Ecological Performance
• Invest-ment in US$
• ROI % (Profit as % of
Investment
• Total Direct Jobs
• Investment per job $/Job
• Jobs for Women
• Other Impacts (e.g. Health)
• Reduction of Local Pollution
• Reduction of CO2 Emissions
• Much Lower Cost of Saving CO2 Emissions
 
Briquetting Machine 125 Kg 9000 6.0 2.1 4286 YES YES YES YES YES
Four Nos. Additional New Pumps 8000 17.0 1.1 7273 YES   YES YES YES
Old Pumps 1000 51.0 1 1000 YES   YES YES YES
Paddy Processing 30000 8.0 5.5 5455 YES YES YES YES YES
Fishery 3000 15.0 1 3000          
Planting 5000 3.5 1.5 3333 YES   YES YES YES
Power Plant 60000 10.0 5 12000     YES YES YES
Other Small Energy Service Units 10000 10.0 2 5000 YES YES YES YES YES
 
126000 9.8 19 6563  